New Automated Compliance Reports
In an effort to enhance oversight and monitoring of the T&E certification process, two new reports will be put into production in the SSO Time and Effort System.
- Time and Effort – Not Certified Report: (Effective date: August 9, 2014)
- The Time and Effort – Not Certified Report allows for enhanced monitoring and oversight during the 45 day certification period.
- The Time and Effort – Not Certified Report will be distributed three times during the 45 day certification period, day 25, 35 and 45. The two 45 day certification periods are January 15 – February 28 and July 15 – August 28.
- Report recipients: Central and Department Administrators with update access to the Time and Effort application and Department Heads.
- Reports will be distributed electronically via e-mail from the SSO system.
- Time and Effort – Out of Compliance Report: (Effective date: July 1, 2014)
- The Time and Effort – Out of Compliance Report allows for monthly monitoring and oversight of effort documents that were not certified during the 45 day certification period.
- The Time and Effort – Out of Compliance Report will be distributed at the first of each month.
- Report recipients: Central and Department Administrators with update access to the Time and Effort application and Department Heads.
- Reports will be distributed electronically via e-mail from the SSO system.
QUESTIONS: Contact Karan Watkins, Director of Time and Effort Compliance in the Division of Research at kwatkins@tamu.edu or (979) 862-1765.
Compliance Report Timeline
Day | Action |
Day 1 | Effort Certification Period Opens January 15 (certification of Fall effort) July 15 (certification of Spring effort) Notification emails are sent every Monday to employees who have items in their inbox that require attention or action.
If an effort document is rejected, an email notification is sent to the department and central administrators at the time the event occurs. |
Day 25 | Time and Effort – Not Certified Report
|
Day 35 | Time and Effort – Not Certified Report
|
Day 45 | Effort Certification Due Date Time and Effort – Not Certified Report
|
Day 46+ | Time and Effort – Out of Compliance Report (Monthly Report)
|