Project news and updates.
- November UpdatesNovember brings us closer to the completion of the Factory Exit phase of the project. The next phase is System Integration Testing (SIT). The team has secured a product that will improve the process for managed file transfers. Accenture was engaged to review the reporting organizational structure and recommend improvements.
- December UpdatesThe FAMIS replatforming and modernization project is close to completing the factory exit stage. This month, test strategy, planning and execution of the project focused on the next major phase – System Integration Testing (SIT). Some code remediation remains to be done, and changes will be delivered in early January 2021.
- January UpdatesThe project has started System Integration Testing (SIT). During this phase we take more control of the software and testing, including installation and configuration. Multiple testing environments are set up to ensure testing is thorough and complete. Testing includes all integrations and most business processes.
- February UpdatesExtreme winter weather in February 2021 contributed to the delay in starting System Integration Testing (SIT). The next delivery goal will bring enhancements to automated file conversion and database column names
- March UpdatesExtreme winter weather in February 2021 contributed to the delay in starting System Integration Testing (SIT). The next delivery goal will bring enhancements to automated file conversion and database column names