News
New
The ServiceNow Steering Committee meets on Wednesday.
The Digital COE Committee meets on Thursday.
Projects
New
Project Helios
- This week marked the end of the Architect phase and completion of the Business Process Workbooks and fit / gap analysis deliverables.
- Configuration of our first prototype (Prototype 1) continues.
- The data conversion team reached the 50% mark of loading data needed for Prototype 1. Thank you to all member data conversion teams!
- The integrations team continued to work on integration design documents.
- Retiring our current HR / Payroll tools:
- The “Payroll Accounting Link” team put the finishing touches on the Workday to FAMIS link design. The team will begin working against summer and fall milestones next week.
- Analysis continued on impacts to SSO applications and the Data Warehouse.
SCIO Trips/Visits
- Dallas (May 31 – June 2)